Reference: David Beebee (Managing Director)

PRINCES FOODS

New Build food processing and bulk cold storage facility.

Ray (Senior Planner) provided planning support for the production of the Tender Programme and Method Statements for the initial bid and further support with the client interview stage helping ADI through to successful contractor appointment and subsequent Construction stage and progress monitoring for the duration of the works to its successful completion.

ADI

£22m

June 2018

July 2019

Long Sutton, Lincolnshire

Tender Programme & NEC Contract Planning

Food Manufacture

JCT with Design & Build and NEC form of contract